Cyclone Narelle tested APA's preparedness and operational resilience across Queensland, the Northern Territory and Western Australia in late March 2026 during a busy cyclone season.
While there was no impact to APA's Queensland assets, teams in the Northern Territory and Western Australia activated cyclone preparedness and response plans.
This included linepacking of pipelines, informing customers and safely relocating people from exposed sites. Following the event, assets were inspected and returned to service safely and efficiently. In the Northern Territory, the main impact of the cyclone was heavy rainfall and flooding that affected already saturated catchments around Katherine.
Despite two significant flood events, APA's preparedness ensured its people and assets remained safe.