East Coast Gas Grid Expansion Plan

APA progressing State 3 of East Coast Gas Grid Expansion.

~$500 million
investment to progress Stage 3
30%
additional gas transport capacity

APA's East Coast Gas Grid expansion plan

Hear from Adam Watson, Chief Executive Officer and Managing Director, on APA's East Coast Gas Grid expansion plan.

CEO and Managing Director, Adam Watson, on APA's plan to deliver pipeline capacity needed to solve projected east coast gas shortfalls.

East coast grid expansion plan network and modelling

250718 Transmission Lng Ecgg Map
260219 Eastcoastgasgrid
Project stages
The expansion will be delivered in a number of stages.
Stage 1 and 2 (completed)

Stages 1 and 2 of the ECGG expansion plan have been completed. These works included construction of additional compressor stations on the South West Queensland Pipeline (SWQP) and the Moomba to Sydney Pipeline (MSP) and have increased gas transportation capacity to the east coast grid.

Stage 3

Stage 3A

APA is investing $260 million to deliver Stage 3A, including three new gas compressors along its existing infrastructure to increase north to south capacity for winter 2028:

Together this will expand:

  • South-West Queensland Pipeline (SWQP) capacity by ~58 terajoules (TJs) per day
  • Moomba to Sydney Pipeline (MSP) mainline capacity by ~10 TJs per day
  • Young-Culcairn lateral capacity by ~39 TJs per day.

Stage 3B

APA is investing $220 million to progress Stage 3B to enable continued early works and procurement of long lead items for the Bulloo Interlink, including purchase of 342km of line pipe and further pre-FID works. This maintains a 2028 delivery for this critical project.

These investments, along with future planned expansions, make it clear that pipeline capacity will not be a constraint to solving projected east coast gas supply shortfalls.3

Future stages

Furture stages (storage) focus on delivering new southern market gas storage to support AEMO’s forecast need for peaking gas-powered generation, as more variable renewable energy is added to the National Electricity Market.

This stage involves the delivery of the proposed new Riverina Storage Pipeline (RSP) in New South Wales (NSW), along with new compression and pipeline infrastructure. Access and approvals and concept design is progressing as part of early works funding.

If progressed, it would add new storage capacity in winter 2028 and 2029. The storage project can be delivered in stages, with ~200TJ of storage online as early as 2028, with the potential to expand to ~500 TJ as early as 2029.

Future stages (expansion) add flexibility and amplifies the investments made in previous stages, delivering capacity upgrades into the Victorian Transmission System (VTS). The potential project will expand APA’s MSP and VTS systems to 350 TJ/day from Young, NSW to Wollert, Victoria through the addition of new compressors, reconfiguration works and new metering and pressure regulation infrastructure.

The ~84% increase in transport capacity into Wollert, Victoria could be delivered as early as winter 2029 as the Victorian market becomes more reliant on northern gas basins.

Impact

Sustainability and Environmental Impact

2025 10 25 Sturt Plateau Pipeline 013
2024 05 21 Kurri Kurri Lateral Pipeline Construction 5
2024 10 11 Kurri Kurri Lateral Pipeline Construction 004
2025 10 25 Sturt Plateau Pipeline 005
2024 03 13 Kurri Kurri Lateral Pipeline Construction 21

APA will continue to engage with the community and key stakeholders throughout the different stages of the ECGG Project. We are committed to building and maintaining relationships with all our stakeholders, to keep you informed about the East Coast Grid Expansion and to ensure your views are heard and addressed regarding specific projects.

To learn more about ECGG we encourage you to engage with us here.

APA will continue to work closely with the local and First Nations community, to maximise project opportunities in the project area that will share the benefits of the project through employment, training, education and community investment initiatives. 

As the project progresses APA will develop strategies for local content, Indigenous participation and social investment.

At the 2022 Australian Pipelines & Gas Association Awards, APA won the Environment Award for good practice cultural heritage management and First Nations engagement on the East Coast Grid Expansion project.

APA will engage early with knowledge holders and provide them with project information regarding the future stages for the East Coast Grid project.  APA will then work collaboratively to design the pipeline in a manner that reduces impacts on the cultural heritage.

1 Stage 3A has reached FID, Stage 3B remains subject to final board approval.
2 A final investment decision will be subject to certain considerations, including policy settings, progress with the Federal Government’s Gas Market Review and final Board approval.
3 Stage 3A has reached FID, Stage 3B remains subject to final board approval. AEMO 2025 Gas Statement of Opportunities, page 87, includes both APA and other pipeline expansions.